Est Weight

Kumar JMember for 25 years 3 months
Created
7
3
0
Dear Friend,

Can anyone guide how to use Est Weight column in P6.

1. What is the use of it?
2. How to use it?
3. Whether S Curve can be generated for early & late dates?

Regards,

Bharath Kumar J

7 replies

Oldest first
  1. 0
    Kumar J ·
    Can anyone guide the use of Est Weight in Primavera P6.

    Regards,
    Kumar
  2. 0
    Khuong Do ·
    Hi Bharath
    Est weight is used for Unit Top-down estimation. Let say you have 1000 unit, base on activity’s Est weight Primavera will deliver units to each activity.
  3. 0
    Khuong Do ·
    You can choose S-curve to display base on early or late date by setting option in Edit -> User Preference -> Resource Analysis.
  4. 0
    Khuong Do ·
    You can choose S-curve to display base on early or late date by setting option in Edit -> User Preference -> Resource Analysis.
  5. 0
    Kumar J ·
    Dear Sir,

    Whether i will have manually key in all est weight values against each activity?

    If i need to enter manually, then, i will check for S Curve as suggested by you.

    Regards,
  6. 0
    Khuong Do ·
    Hi.
    That’s right, you have to key in Est weight for each activity base on your experience.
    Then run Top down estimation in Tool menu.
  7. 0
    Siddic K ·

    Hi ,How to calculate the

    Hi ,

    How to calculate the resources in tentative stage and how to apply in P6. 

    Please anybody help me with some example....

     

     

     

     

    Thanks 

    Siddic K

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?