summary totals in p6

Glen StauntonMember for 21 years 2 months
Created
3
2
0
Anybody come accross a possibly glitch with the P6 summary totals that they have had resolved.

On a 5 day working week calender I’m getting a total of 308 days when the start date and the end date of the summary band are 09/11/09 and 02/06/10 respectively.

I’ve checked all the usual suspects, that i’m using the correct duration, calender, summary check box, user preferences etc....

Thanks in advance

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Glen

    Did you check the default calendar?

    Regards
    Dieter
  2. 0
    Glen Staunton ·
    Cheers Dieter, I did and got the problem fixed! Too many variables in this version of Primavera. I need to create a few filters to run to make sure that what I’m sending out is as I assume!
  3. 0
    Armana Jones ·
    it seems your activity calendar and default calendar that used by summary is different.