Why Resources Cost become Zero while updating % complet

Shanmugam ThangamuthuMember for 21 years 8 months
Created
2
3
0
Hi,
In P6 I have a problem while updating progress percentage (Duration) complete the resources cost become zero and the budgted and earned values varies.
How can I solve this?

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Ajith

    Have a look in the view projects --> Calculations --> "Recalculate Actual Units and Cost".

    The following is out of the "Help"-function:
    "Recalculate Actual Units and Cost when duration % complete changes: Mark to estimate actual units and costs as

    Actual (units or costs) = Budgeted (units or costs) * Duration % Complete

    If an activity does not have any resource assignments, Actual units or costs are calculated using the activity’s budgeted units or costs.

    The Project Management application performs these calculations whenever you update the Duration % complete.

    Values you specify override the module’s calculated values. If you do not mark the checkbox, the module does not estimate actuals and the actual fields remain blank unless you specify values." (end of quotation)

    I assume this parameter is the reason.

    Regards
    Dieter

  2. 0
    Shanmugam Thangamuthu ·
    Thanks Dieter.
    The problem is solved.
    In activity table in resources tab I remove the check to De-link the column "Cost unit Linked". Now it is ok.

    Ajith