How does the project calendar and resources calendar work and which one of the calendar take preceedent over the other on a project?

How does the calendars work individually and together?

How do the calendars affect manhours and durations in P6?

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Mark

    An activity is task- or resource dependent (activity type). Depending on this entry, the activity- or the resource-calendar will be used for calculation.
    The summary bars depend on the default calendar.

    Dieter