Duplicating a WBS in P6

Farzin FarsiMember for 17 years 11 months
Created
7
5
0
Hi there,
I am trying to duplicate a WBS (or set of activities) in one project. The problem is I’d like to have a different prefix for each set (different stations in the project) but exact the same number. And this needs to happen more than 30 times.

I wish there was an option in WBS area like whenever you are to paste a WBS it would ask for newly added activities prefix.

Anyone knows the fastest way to do so?

Thanks in advance

7 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Farzin,

    Before copying the WBS go to --> Enterprise --> Project, highlight the current open project --> Project Details --> Defaults tab, Auto-numbering Defaults, in Activity ID Prefix change the value and untick the check box next to "Increment ID based on selected activity".

    When done, go to Project --> WBS and copy the WBS including activities.

    Hope this helps.

    Regards,

    Arnold
  2. 0
    Farzin Farsi ·
    Thanks Arnold,
    This changes both prefix, and number. what if I’d like to keep the number and only change the prefix?
    PS: Because ID numbers do not obey any sort of steady increment I need to keep them in their order.
  3. 0
    Arnold Puy ·
    Hi Farzin,

    There is a workaround, try this:

    Say for example: You want to copy AB1000, AB1010, AB1020...& etc...Then you want to become BA1000, BA1010, BA1020...& etc...

    First, do the global change, where:

    user_text1 = SubString(Activity ID,3,20)

    Then the result is user_text1:
    1000, 1010, 1020....& etc...

    When done, perform the steps in Post #2.

    After that, filter all the newly copied activities and run a global change again, but this time with combination parameters, Where:

    Activity ID = LeftString(Activity ID,2) & user_text1

    Let us know if you have done this.

    Regards,

    Arnold
  4. 0
    Farzin Farsi ·
    Thanks Arnold,
    That was a great help.

    Cheers
  5. 0
    Vladimir Liberzon ·
    Interesting that in Spider Project this function is standard.
    We recomend this approach to activity coding of similar fragnets.
    Best Regards,
    Vladimir
  6. 0
    Sean Moghimi ·
    Hi Farzin,

    In Primavera P6 V.7, new version that Oracle released 2 days ago, there is a new function to renumber the activities or change prefixes with variety of options. You may as well want to give it a try...

    Cheers.
  7. 0
    Farzin Farsi ·
    Thanks Sean, I’d whenever get a chance. I’m still stuck to P6.2.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?