“physical % complete” column problem (on WBS summary)

Izam ZakariaMember for 20 years 4 months
Created
4
2
0
Hi

I’ve filled up “physical % complete” for each activity but the problem is it doesn’t display on WBS Summary.
I clicked already the “show grand total” but it’s not happen on “physical % complete” column. Gents what should I do?

Thanks for your attention

4 replies

Oldest first
  1. 0
    Arnel Lagumbay ·
    Hi Izam,

    Physical % complete will not roll up to WBS summary,my advice is do on excel manually.Try to use Duration&Units percent complete,it will roll up to WBS summary.

    I hope it will help...


    Best regards,
    Arnel
  2. 0
    Arnold Puy ·
    Hi Izam,

    Your schedule is a resource cost loaded?

    Regards,

    Arnold
  3. 0
    Izam Zakaria ·
    Arnold

    Mine was budgeted units loaded. Do you have any idea?
  4. 0
    Arnold Puy ·
    Hi Izam,

    You must have cost loaded in your programme. Besides, "Physical % Complete" doesn’t roll-up in the summary band, but there is a workaround.

    Try to convert your Budgeted Units into Cost by just assigning Price/Unit to the Resource.

    Likewise,there is a workaround to convert your "Physical % Complete" into "Performance % Complete" and will roll-up in the Activity & WBS Windows If you have assign Cost to your Task.

    Regards,

    Arnold