Budgeted Units were Multiplied by 8

Dinesh Kumar DamavarapuMember for 24 years 7 months
Created
4
2
0
Dear All,

We have recently recived a schedule from the contractor which was developed in P6 and when we imported it, all the budgeted units were multiplied by 8.

Could anybody advice me on how to fix this?

Thanks & regards

Dinesh

4 replies

Oldest first
  1. 0
    Jason Jarrett ·
    Hello,

    You can simply correct the budgeted units by performing a global change. You must be able to filter on the activities needing the change. If interested, let me know & I can walk you through.

    Jason
  2. 0
    Anoon Iimos ·
    that’s the difference between the planning unit used; it may be in Hours or in Days...
  3. 0
    Arnold Puy ·
    Hi Dinesh,

    In addition to Anoon info.

    According to you that all Budgeted Units were multiplied by 8. If you are using P6 it means that your setting in Edit --> User Preferences --> Time Units tab, "Unit of Time" is in "Hour" just change it to "Days".

    Regards,

    Arnold
  4. 0
    Dinesh Kumar Damavarapu ·
    Hi Arnold,

    That worked, Thank you.

    Dinesh