The trivial that I couldn’t fix (red bar issue)

Izam ZakariaMember for 20 years 4 months
Created
2
3
0
Ermm I would like know why the bars chart shown red color once we assign them as constraint activity? It’s totally different with P3 when the bar charts still remain in green color unless it was a zero total float.

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Izam

    Under the scheduling options you decide, from which total float the bars turn to red. "F9" --> Options

    Regards

    Dieter
  2. 0
    Francis Moyalan, PMP,PMI-SP ·
    Izam,

    Further to Dieter’s response to your query, I would like to throw some light on this issue.

    You can do it in the bar format option and unlike in Ver 3.10 here, you could filter the critical activities and you’ll decide which activities shall be shown in red. In your case you can filter activities on Longest path to be in Red which may resolve your problem here.

    Regards,

    Francis Moyalan Varghese