Updating the assigned base line

Sanjay RaoMember for 18 years 4 months
Created
3
2
0
Hi every one
During updating the assigned base line ( maintaining baseline ) to a project do we need to update the activity/ milestone assigned in revised program.

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Sanjay,

    Which one do you want to update, Baseline or Revised Programme?

    Regards.
  2. 0
    Sanjay Rao ·
    i want to update Base line
  3. 0
    Arnold Puy ·
    Hi Sanjay,

    There are two ways on how to update your Baseline.

    1. Restore your Baseline Schedule and update it in accordance to your new data date and % complete, and whatever you need to update.

    2. You can update without restoring but this is more complicated than #1.

    It depends on what you want to update in the "Update Baseline Options".

    Regards,

    Arnold