Skip to content

Baseline Problem in P6

Mohammed Awab EziddenMember for 19 years 10 months
Created
2
2
0
Hi everybody,

I have a little problem in assigning target to my update program When I assign previous update as a project baseline for many resoene I found all dates having Actual dates in baseline dose not appear in project baseline columns or P6 show Dates same as original baseline and sometimes same as Data_Date and
I’ve noticed all schedule percentage are wrong and calculated as per first assigned baseline!!!
In p3 everything was going Ok
Any one has answer and can help me???

Thanks and regards for ALL

2 replies

Oldest first
  1. 0
    Mark M ·
    Greetings

    If I understand your problem correctly. check your Admin Preferences; Earned Value tab;
    At the bottom of that screen (under the Earned Value calculation heading) is a drop down box with 3 options, I believe yours would be set to "Budgeted values with planned dates"?
    If you change this to "Budgeted values with current dates" you should get the result you’re after.

    Hope that helps.

    Regards
    Mark

  2. 0
    Mohammed Awab Ezidden ·
    Thanks a lot Mark ,
    Really I appreciate your helping ,
    Problem has been solved, your answer was correct.

    Good man

    Best regards

    Mohammad Awab

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?