Displaying -ES and EF in day number instead of date
In the Open Standard
KI
Kumar IMember for 23 years 3 months
- Created
- 12
- 6
0
Hi all,
Can any one inform urgently what options to select in P6 to display the early start and finish dates as day number ,instead of dates.This is for submission of tender program,where the project start date is not yet decided.
Thanks in advance
Kumar
Can any one inform urgently what options to select in P6 to display the early start and finish dates as day number ,instead of dates.This is for submission of tender program,where the project start date is not yet decided.
Thanks in advance
Kumar
12 replies
Oldest first- 0APArnold Puy ·Hi Kumar,
What do you mean dates as "day number", like what? You must cite an example. Date like 20.10.09 instead of 20-Oct-09?
If you need date like 20.10.09 then go to Admin --> User Preferences --> Dates tab, Options, untick the "Month name" and change the Separator to (.)
Regards,
Arnold
- 0VLVladimir Liberzon ·Arnold,
it is natural desire.
When project start date is not known and you need to submit proposed project schedule you may show that some activity will be done on 62nd day from the project start and not on the certain date.
This situation is rather usual when you need to submit the proposal or bid.
Best Regards,
Vladimir - 0APAlan Phillips ·Kumar,
Right click on the screen in the barchart area of the screen.
Left Click on timescale.
Check "Show Ordinal Dates"
Choose "Ordinal Date Interval" and select the unit you want.
Un-check "Show Primary Dates"
Apply these actions and this should give you what you are looking for.
Kind Regards
Alan
- 0APAlan Phillips ·Kumar,
Right click on the screen in the barchart area of the screen.
Left Click on timescale.
Check "Show Ordinal Dates"
Choose "Ordinal Date Interval" and select the unit you want.
Un-check "Show Primary Dates"
Apply these actions and this should give you what you are looking for.
Kind Regards
Alan
- 0APAlan Phillips ·Kumar,
If you want to show the day numbers for each activity in columns, try the following work around.
Go to Tools, Global Change, New.
Go to the middle section of the change under "Then" and click "Add"
Under Parameter select "user_start_date1"
Under "Is" select "="
Under Parameter/Value select {Custom} and then enter the start date for your project. eg 1-Oct-09
Then click Add to add another line.
Under Parameter select "user_integer1"
Under "Is" select "="
Under Parameter/Value select "Early Start"
Under "Operator" select "-"
Under Parameter/Value select "user_start_date1"
Then click Add to add another line.
Under Parameter select "user_integer2"
Under "Is" select "="
Under Parameter/Value select "Early Finish"
Under "Operator" select "-"
Under Parameter/Value select "user_start_date1"
Run the global change and this will calculate the start and finish date number.
Under Columns show user_integer1 and user_integer2.
Under Group and Sort uncheck "Show Group Totals" if this box is checked.
This should then give you the start and finish day numbers.
I am assuming that you are not using any of the custom fields I mention above for anything else!
Hope this helps!
Kind Regards
Alan
- 0JCJayan Chacko ·
Further to Alan's workaround
Further to Alan's workaround it must be noted that the ordinal dates obtained from this workaround display dates based on working days only (Depending on the activity calenders). So say if you have a project with activities using different calenders and different no. of working days, don't be surprised to see Ordinal end date of the project not matching with the project duration (which usually is expressed in Calender days).