Global Change

Online AloneMember for 16 years 11 months
Created
3
1
0
Dear All,

I need to assign certain dummy-resource to be loaded for all activities.

The Tools/Global Change/Activity Resource Assignments doesn’t response for blank resource’s activities.

Is there such unique statements in order to assign single resource for all activities at once by using the global change tool? Assuming that, all activities are not resourced initially.

Please advice.

3 replies

Oldest first
  1. 0
    Sanjay Rao ·
    Select All activity then right click choose assing resource - select required resource to be assigned to activity.
  2. 0
    Online Alone ·
    Dear Sanjay,

    Thank you, I got the point.
  3. 0
    Sanjay Rao ·
    you are welcome