How can I add the same code to various activities the quickest? The same with resources

2 replies

Oldest first
  1. 0
    D Artagnan ·
    U can utilize activity6.xls file to the job.
  2. 0
    Kaide Johar Manasi ·
    You can use import export facilities from within P5/P6. While exporting select Activity Codes. In your xls file, add this codes and import back.