Customizing Timeline

Ruel CamaquinMember for 17 years 11 months
Created
1
1
0
Guys,

Is there a way that i could replaced the timeline dates (second line or thirdline) M to S (monday to sunday) interval date to numbers?

Regards,

Ruel

1 reply

Oldest first
  1. 0
    Mark M ·
    Hi Ruel

    Right click in the Gantt chart, select Timescale, under "Date Format", select "Show Ordinal Dates" & the necessary interval you require.
    Note: If you select Ordinal Start as PS (Project Start) it will be based on your "Planned Start" date in the Projects screen, Dates tab.

    Hope that helps.

    Regards
    Mark