Schedule % Complete in P6

Athar HashmiMember for 17 years 6 months
Created
3
1
0
Dear Guys,
when i am executing the ’update progress’ command then ’schedule % complete’ shows the %age progress for each activites but it isn’t showing the %age of the ’summary’ or ’project summary’ of thses activities.

How can I know the overall progress of the project? pls help.

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Athar,

    Is your programme cost loaded? If not then you need to allocate the cost.

    Regards,

    Arnold
  2. 0
    Athar Hashmi ·
    Tanx Arnold,
    its working
  3. 0
    Arnold Puy ·

    You are welcome Athar.