Tracking the schedule in P6

Miguel RiosMember for 17 years
Created
2
1
0
Hello guys,

Once you have your baseline schedule in P6, can you please tell me how you do the first track? I know you use the Update feature in P3, just trying to find out how you do this in P6.

Thanks.

2 replies

Oldest first
  1. 0
    Mk Tse ·
    update feature also available on P6. However, in-project project cannot be used as baseline on P6
  2. 0
    Rezvan Zeinali ·

    Hi Everyone, Is there anyone

    Hi Everyone,

    Is there anyone here have any idea how to use tracking tab in p6?