Global Change in P6
In the Open Standard
CB
Cristina BostonMember for 17 years 2 months
- Created
- 13
- 4
0
Good morning,
Here is what happened to me: I used Global Change to assign Bell Curves to my labor resource. The resource was loaded with budgeted dollars. After applying the Global Change...guess what: all my dollars dissapeared.
My question is: did I do something wrong? Is there any way to recover the data (budgets)? My P6 was downloaded as a stand-alone software, on my personal laptop.
THank you so muh for your answer.
Here is what happened to me: I used Global Change to assign Bell Curves to my labor resource. The resource was loaded with budgeted dollars. After applying the Global Change...guess what: all my dollars dissapeared.
My question is: did I do something wrong? Is there any way to recover the data (budgets)? My P6 was downloaded as a stand-alone software, on my personal laptop.
THank you so muh for your answer.
13 replies
Oldest first- 0EMErnesto Montales ·Cristina,
One reason I can think of is the source file you imported doesn’t have the budget data or delete row is turn on.
You could go back to the source file and check it if it contains the budger data you can restore it all again.
Unfortunately there is no way you can recover the data, there’s no undo function. What you can do to prevent it from happening again is before you do any global change be sure that you keep a back up for security.
Hope this help.
Regards,
Ernesto
- 0RDRafael Davila ·Cristina:
You can backup your database as per the following reference,
http://primavera.zxlm.cn/kb/prim54984
This will backup all your jobs and enterprise data.
You can also keep separate individual copies of individual jobs in your database, this will be faster, and only specific job data will be stored within your database, your enterprise data will not be backed up.
Backup your database to another hard disk.
Murphy is always around.
If "Boston" in your name is because you are from Boston, it means you will soon get very cold. I survived the Blizzard of 78 when the fifth army came to the rescue of the Mass. National Guard. Just remember, there is hope for a better life, in middle of January I will be on my backyard in shorts having a Pina Colada (LOL).
Best regards,
Rafael - 0APArnold Puy ·Hi Cristina,
I guess you have done something wrong. If you had just assigned a curve to your resource using global change then the cost should not disappear. The parameter should look like this:
Select Subject Area "Activity Resource Assignments"
Where: Resource ID Name "is under" "Resource ID"
Then: Curve "=" Bell Shaped
Regards,
Arnold
- 0RDRafael Davila ·Arnold,
Assuming no longer the budget data is there because the global change erased the data; can you transfer the budget from a baseline schedule?
Usually the budget amounts from a baseline to updates does not changes by much, is on actual and progress where most of the changes are.
If Cristina has a baseline schedule with your help a lot of time might be saved.
Best regards,
Rafael - 0APArnold Puy ·Hi Rafael,
In the case of Cristina, if she has a baseline schedule assigned to the current schedule or she kept a backup copy of the baseline then yes she can recover the budget data from the baseline to the current schedule. If how? Then there are two ways to perform the procedure:
1. By using the Update Baseline. This is little bit complicated.
2. By using the Import/Export --> Spreadsheet - (XLS). This is the easiest way.
Regards,
Arnold
- 0APArnold Puy ·Hi Cristina,
In some cases, the "is under" and "equals" are similar. If you don’t mind, can you tell us in detail what happen why your budgeted data disappear?
As I have mentioned in my previous post that, if you had just assigned a curve to your resource using global change then the cost should not disappear.
Regards,
Arnold
- 0CBCristina Boston ·Arnold,
I had 2 resources for this project: M, L for Materials & Labor.
I used the Material Budgeted Cost, Labor Budgeted Cost & Non-Labor Budgeted Cost columns to load the $ amounts. The Total Budgeted Cost column added them automatically.
After doing that, I created a new Global Change to assign the Bell Curve to the above resources. I started with the materials. Then I created a new one for labor.
WHEN: Resource ID is equal M
THEN: Curve = Bell Shape
After Commiting the Change...all my cost columns showed $0.00.
- 0APArnold Puy ·Hi Cristina,
In my experienced, when your Resource’s Price/Unit is equal to Zero (0), the Budgeted Cost will automatically equal to zero when you applied any "Global Change" or "Recalculate Assignment Cost". I think this is the reason why your cost was disappeared.
In order not to affect your cost-loaded assign to the activities, prior to assign any resources with zero price/unit, in the Resources Details tab, remove the check box next to "Calculate cost from units" then you can now assign the resources.
Otherwise, you can set your Budgeted Units equal to Budgeted Cost and set your Price/Unit equal to One (1). Or you can try to utilize the Project Expenses.
You can try this and let us know.
Regards,
Arnold
- 0CBCristina Boston ·That must be it Arnold,
I had no Price/Unit for my Resources.
Thank you all for your intput. It was most helpful.
Should I add that not only Global Change does this? One of my coleagues, after noticing what happened to me, started to add the Resource Curve one by one to each activity. Guess what! It still deletes the budgeted cost for that respurce (if the cost was already loaded).
My conclusion: whatever you do, loading the schedule with budgeted $ should be the last task to perform.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?