Resources & Calendars

Alaa Al hajMember for 18 years 11 months
Created
8
3
0
God day

In Primavera P6 How we can create different rates for One Resource and link those rates with calendars

Example let us say we have 3 calendars
Cal 1 8 working hours
Cal 2 10 working Hours
Cal 3 12 working Hours

And we have 2 Resources
Resource 1 = Labor
Resource 2= Mechanical technician

So for labor we have 3 rates 3$/H for Cal 1
4 $/H for cal 2
4.5 $ / H for cal 3

So what I want is if I change the calendar for activity the rate of resources that assigned to this activity should be changed and of course the cost will be changed
Is this possible in primavera P6



Regards
ALAA

8 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Alaa

    I don’t believe, this is possible. Rates are related to resources.
    A solution might be to use three resources with different calendars and rates and activity type "resource dependent".

    Hope this helps

    Dieter
  2. 0
    Alaa Al haj ·
    Thanks Dieter,

    Actually it is very useful and i can use it
    but it is time consuming but at least we know the long solution now searching for the short

    thanks again
    Alaa
  3. 0
    Vladimir Liberzon ·
    If to use different resources instead of one it will be hard to study resource requirements and workloads.
  4. 0
    Dieter Wambach ·
    Vladimir

    In my opinion Alaa didn’t want to do a real resource planning, just to get costs and overall workload. He will easily be able to show a summary curve.

    Per assignment the rate can be modified, this will take longer.

    Alaa

    You can easily replace a resource by another one for a group of activities:
    Select the assign-resource icon on the right border of the P6 Window. --> Select all activities where you want to replace resource "Labour" by e.g. "Labour1" --> Select resource "labour" then icon "replace by" --> an additional window will open --> select resource "labour1" --> assign.

    Regards
    Dieter
  5. 0
    Alaa Al haj ·
    Thanks
    i will try the two ways
    but it seems it is not available in p6 to change the resource rate whence you change the activity calendar
    am i right

    thanks
    Alaa
  6. 0
    Dieter Wambach ·
    Alaa

    You’re right. 5 rates per resource to be selected by default for a project, can be overwritten by assignment (resource to activity): Different rate, different choice from those 5 rates, from roles or budgeted price for the activity.

    Just had another idea: If you want to use only one resource, use roles. Assign the resource to 3 different roles with different rates/unit --> create Global Change (group: Resource Assignments) Rate source=role --> assign the calendars --> group by calendar --> select all activities belonging to one goup --> assign appropriate role to each group. If you have one resource per activity, you can use view "Activities", esle view "Assignments".

    Selection of rate following calendar not possible - only programming API or SQL.
    Regards
    Dieter
  7. 0
    Alaa Al haj ·
    Thanks Dieter
    i use the following technique to solve the problem
    i keep the same resource
    but i change the effective date for each rate that i want
    in my assignment i have 10 different rates
    so for example for Resource ( Helper / labor)
    i create 10 rates with different effective dates
    so i will just change the effective date to suit the schedule
    it is working
    and i am still working on your options since they are more professional
    please i will come back to you for further assistance
    sorry for taking your time but this how the beginner like me use the professional like you

    thanks
    Alaa
  8. 0
    Dieter Wambach ·
    Dear Alaa

    You’re welcome

    Dieter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?