Dear friends

Can we make back up like P3 in P6 ???

With regards
Arun.V

4 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Arun,

    You mean back up a project. If yes, then go to File Menu --> Export --> Primavera PM/MM - (XER).

    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=67775

    If database, then it is a long story... Anyway, I highly recommend to read the Primavera Manual.

    Regards,

    Arnold

  2. 0
    Arun Vasanth ·
    Hai Arnold
    Thxs

    Again my qurie is
    before we were taking the back ups of monthly updations and keeping it in the Back up folder.When ever our top management needs the monthly updated program.We were sending the updated program of particular month along wit h the base program.Is this possible in P6.

    With regards
    Arun.V
  3. 0
    Arnold Puy ·
    Hi Arun,

    If you export the .XER file along with the baseline, only the current open project will be exported. The baseline will stay in your project.

    You can do one thing, keep a copy of a baseline in your folder, then what you need only is to export the monthly updated programme.

    It means you need to send them individually.

    Regards,

    Arnold

  4. 0
    Mk Tse ·
    open you current project (monthly update) and baseline project at the same time. Then export them into XER format, a XER will be created with two projects inside

Log in or join to reply