Primary base line
In the Open Standard
Shanmuga Pandian ThangaveluMember for 20 years 3 months
- Created
- 9
- 2
0
B1 -is a orignal contract file data date- 1/10/09
B2 -is a copy of B1 update file data date 1/11/09
B3 -is a copy of B2 update file data date 1/12/09
Now - B3 is a current project
- B2 is primary baseline
Problem :
ACT File Start finish
Waterproofing B1 10/10/09 20/12/09
Waterproofing B2 Actual 20/10/09 10/12/09
but in my cuerrent project B3, I kept B2 is a primary baseline but my bar and Base line 1 start and finish date shows as 10/10/09 and 20/12/09
Please give advise how can I show B2 date in B3 as a baseline?
Regards ,
T.Shanmugapandian
Senior Planner
B2 -is a copy of B1 update file data date 1/11/09
B3 -is a copy of B2 update file data date 1/12/09
Now - B3 is a current project
- B2 is primary baseline
Problem :
ACT File Start finish
Waterproofing B1 10/10/09 20/12/09
Waterproofing B2 Actual 20/10/09 10/12/09
but in my cuerrent project B3, I kept B2 is a primary baseline but my bar and Base line 1 start and finish date shows as 10/10/09 and 20/12/09
Please give advise how can I show B2 date in B3 as a baseline?
Regards ,
T.Shanmugapandian
Senior Planner
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?