Global Change

Arun VasanthMember for 17 years
Created
4
4
0
Dear friends
If Iam making a change in one project programe

eg font size ,Items in the columns .


The same change is reflecting when I am opening som other programs .Is there any solution to avoid this one ???


Is there any way to update automatic ??
I want to update after giving all the progress in one shot
Fix the data date update ...

Any body guide me ??

One more
How to find the planned percentage & Automatic percentage ???

With regards
Arun.V

4 replies

Oldest first
  1. 0
    Mk Tse ·
    If Iam making a change in one project programe
    eg font size ,Items in the columns .
    The same change is reflecting when I am opening som other programs .Is there any solution to avoid this one ???

    (Save layout rather the keep using the default)
  2. 0
    Mk Tse ·
    Is there any way to update automatic ??
    I want to update after giving all the progress in one shot
    Fix the data date update ...

    (what is your meaning of "update", auto-scheduling or others)
  3. 0
    Mk Tse ·
    How to find the planned percentage & Automatic percentage ???

    (display the field in column)
  4. 0
    Wilfredo Jr. Flores ·
    If Iam making a change in one project programe

    eg font size ,Items in the columns .


    The same change is reflecting when I am opening som other programs .Is there any solution to avoid this one ???

    reply=you can save a lay-out for each project.the last lay-out that you used will appear in the new project that you will open


    Is there any way to update automatic ??

    ===>>check tools, update progress. check if you want to update only highlighted activities or all activities.


    I want to update after giving all the progress in one shot
    Fix the data date update ...
    ===>>>fix the data date or store actuals?


    Any body guide me ??

    One more
    How to find the planned percentage & Automatic percentage ???

    ====>>>>you can use "schedule %" and show it in the columns
    automatic percentage is click tools, update progress


    hope this will help you

    With regards
    Arun.V

Log in or join to reply