Skip to content

Unable to change baseline

Rangarajan RamaswamyMember for 16 years 10 months
Created
3
2
0
i have created & assigned my baseline to my project,but now i want to change it . and i am unable to.

Also whenever i press F9 to schedule my project some of the activities automatically shifts to the current data date.
PLZ help

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Raj,

    1. Go to Project --> Assign Baselines, Change your Project Baseline or Primary to "Current Project". When done, again, go to Project --> Maintain Baselines, highlight the baseline then select restore. Now you can change and assign a new baseline.

    2. Check the predecessors/successors of these activities. I guess, it is an open-ended activities.

    Regards,

    Arnold

  2. 0
    Izam Zakaria ·
    Pal,

    It’s working man

    Thx
  3. 0
    Arnold Puy ·

    You are welcome.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?