Baseline dates not matching Actuals

Simon DaviesMember for 16 years 10 months
Created
4
2
0
I have recently taken over another planners P6 programme. I have deleted all existing baselines and trying to take a project initial baseline (the programme has had actuals placed onto it already)

When I assign the new project baseline the dates do not match the Start/ Finish dates. The dates are taking the planned Start/ Planned Finish dates.

Why???

Does anyone know how I can baseline the current project dates, NOT the planned start/Finish dates.

Thanks

4 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Simon,

    Welcome to Planning Planet..

    Try to check your Admin --> Admin Preferences --> Earned Value, Earned value calculation, change it to "Budgeted values with current dates".

    Regards,

    Arnold
  2. 0
    Simon Davies ·
    Thanks for your reply. When I try to change these areas, they are grayed out. I have Super User rights and have tried changing settings in WBS, Activity and Project views.

    Any thoughts to why this is happening?
  3. 0
    Simon Davies ·
    I have success!! I got my Admin user to change these settings, and now all dates match actuals! Both my Admin user and myself are very gratefeul. Thank you
  4. 0
    Sunil Babu ·

    Hi ArnoldThans for this

    Hi Arnold

    Thans for this useful information..

    Regards.

    Sunil

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?