EXTERNAL ACTIVITY RELATIONSHIP GONE AFTER IMPORTING

Wilfredo Jr. FloresMember for 21 years 1 month
Created
4
2
0
Dear all,

I have imported our baseline programme from my manager’s computer. It consists of 7 different projects under one EPS. I made sure that the settings are correct like import external relationships. I tried to export it in one xer file and import to my computer and also 7 xer files and imported it one by one but the external relationships was gone. can anyone has a solution for this?

4 replies

Oldest first
  1. 0
    Mk Tse ·
    must export and import all XER at the same time
  2. 0
    Wilfredo Jr. Flores ·
    Thanks. I’ve done exporting all projects in 1 xer but still, i encountered the same problem. Also, I noticed asterisk marks in the dates and i found out that it was caused by external dates which are acting as constraint
  3. 0
    Mk Tse ·
    Please review individual setting when import
  4. 0
    Wilfredo Jr. Flores ·
    individual settings are ok like import external relationships, activity relationship, activity resurce assignment and the action is update existing but still the relationships are gone. What i noticed from the original file, I can’t go to some successors and predecessors activities, then when I transfer it to other PC, these relationships that the GOTO function was disabled were not imported.

    Thank you very much for your help :-)