Dear All,

Looking at the log generated by P6, there are some vague statements such as:

-Milestone Activities with invalid relationship

-Activities with unsatisfied Constraint

-Activities with unsatisfied Relationship

-Activities that are not on any paths

your immediate help is highly appreciated

thanks

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Wilfredo,

    1. The Scheduling Log will report Finish-to-Start Relationships as invalid. The Finish-to-Start Relationship Type is a valid Relationship to all Activity Types. The issue is specific to the Scheduling Log incorrectly flagging Relationships as invalid between Milestones and has no effect on Scheduling.

    2. If constraints cannot be satisfied because of logic, they would be listed under unsatisfied constraints. Also, there may be an unsatisfied constraint because, as the data date moves forward, a date constraint can simply be bypassed. Activities with constraints show in log file as unsatisfied if activity has not been completed/finished.

    3. The activities with unsatisfied relationships are reported any time a relationship is not honored, because of constraints.

    4. Activities that are not on any float path are shown for information only and do not indicate any error in the schedule. To remove them from the log, schedule the project without using multiple float paths. This section of the schedule log only appears when using the advanced scheduling option, to calculate multiple float paths. This option specifies a maximum number of float paths to be calculated; therefore, all activities may not fall within a float path.

    Regards,

    Arnold

  2. 0
    Wilfredo Jr. Flores ·
    Hi Arnold,

    Thanks for your help. I appreciate it a lot.
    Anyway I send a private message to you


    Thanks again

    Wilfredo
  3. 0
    Arnold Puy ·
    Wilfredo,

    You are welcome.

    BDW, my email is primavera6@live.com

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?