Global Change

Albert BalogoMember for 18 years 4 months
Created
3
1
0
Hi Planners,

Do you know how to load the defferent types of resources in P6 using global change into the multiple activity code, like the way we are doing in P3.


Your assistance is highly appreciated

Regards

Albert



3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Albert,

    Unfortunately, you can’t allocate resources using global change.

    Try to use the easiest way by just filtering your activities using your activity code and select all activities by pressing the shift from your keyboard and select "Assign Resources" located at the right corner of your monitor.

    Regards,

    Arnold
  2. 0
    Albert Balogo ·
    Hi Arnold,

    Thanks a lot for your advised, that technique is useful.


    Regards,

    Albert
  3. 0
    Arnold Puy ·
    Hi Albert,

    You are welcome.