Primavera P6 System Performance
In the Open Standard
John FosterMember for 24 years 4 months
- Created
- 10
- 4
0
We have recently implemented Primavera P6 onto a project and the planners using the system feel that the time taken to Analyse/Schedule the project of around 10,000 activities is excessive.
The DBA’s of the system cannot see any problems on the server side.
There are only a limited number of users on the system at present so we are concerned that when P6 gets rolled out across the wider planning community and their associated projects there will be severe system degradation.
I’m interested in anyone using P6 with large project networks, the number of Activities, the number of users and the time taken to schedule the projects.
The DBA’s of the system cannot see any problems on the server side.
There are only a limited number of users on the system at present so we are concerned that when P6 gets rolled out across the wider planning community and their associated projects there will be severe system degradation.
I’m interested in anyone using P6 with large project networks, the number of Activities, the number of users and the time taken to schedule the projects.
10 replies
Oldest firstLog in or join to reply