Inserting a ’Tick Box’ into a P6 Layout

Nigel BurnMember for 19 years 2 months
Created
2
4
0
Hi All,
I need to show a ’Tick Box’ (or Checkbox) in my P6 layout, which will be used as an alternative to an ’Indicator’ field.

Can anyone offer any suggestions or steps to include this field in my customised layout.

Any assistance will be greatly appreciated.

Thanks.

2 replies

Oldest first
  1. 0
    Mark M ·
    Hi Nigel

    If you’re not using Top Down Estimation you could possibly use the column "Lock Remaining" & give it a new/custom title. This column can be manually ticked or unticked by the user.

    Using "Hint Help" on Lock Remaining: "Indicates that the budgeted labor & nonlabor units for the activity will not be modified by top-down estimation"

    Just a thought as I’ve never required a tick box (check box) myself.

    Regards
    Mark
  2. 0
    Nigel Burn ·
    Mark,
    Thanks for the info. It is exactly what I am looking for.