P6.1 Assign resources fixed budget units problem
In the Open Standard
Abeer MahmoudMember for 18 years 3 months
- Created
- 2
- 4
0
Dear All,
Kindly note that I have a project with 500 activities and I assigned resources for it but I have a big problem:
I have resource R#1 18h/d and for example I assigned it to activity AB with budget unit = 100hrs this activity duration is 15days.
When I changed this duration to 18 days this budget units changed automatically to 120 hours which not correct/applicable at all I need to fix the budget unit to be 100hrs even I change the duration.
How can I do this by default way please by steps and kindly note that it is urgent?
Best Regards,
Abeer
Kindly note that I have a project with 500 activities and I assigned resources for it but I have a big problem:
I have resource R#1 18h/d and for example I assigned it to activity AB with budget unit = 100hrs this activity duration is 15days.
When I changed this duration to 18 days this budget units changed automatically to 120 hours which not correct/applicable at all I need to fix the budget unit to be 100hrs even I change the duration.
How can I do this by default way please by steps and kindly note that it is urgent?
Best Regards,
Abeer
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?