Skip to content

Baseline Schedule

Moutaz AldeibMember for 22 years 9 months
Created
4
1
0
Dear Planners,

Can I find the baseline schedule after assigning to the project? Can I find it and open it?

Regards,

Moutaz

4 replies

Oldest first
  1. 0
    Mimoune Djouallah ·
    hi moutaz;

    i am afraid you can’t, first you have to restore it, it is not like p3.

    best regards

    ps: i really hope that i am wrong on this point.
  2. 0
    R. Catalan ·
    Moutaz,

    Yes, you can find it.

    First, unaassign the Baseline, select Project Menu, then Assign Baselines, then unassign the Baseline.

    Second,restore the Baseline, select Project Menu, then Maintain Baselines, then highlight the Baseline, then click Restore.

    Go to Project Window (Enterprise, then select Projects), select the Baseline you just restored and open the project.

    Hope the above helps.

    Best regards,
    R. Catalan
  3. 0
    Mimoune Djouallah ·
    catalan

    i just miss P3 way of dealing with baseline, it is so logic and intuitive.

    best regards
  4. 0
    Moutaz Aldeib ·
    Thanks Catalan for your information, I have got it, but this will unlink the baseline as a new project where you can modify.

    Regards,

    Moutaz

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?