Oldest first- 0RDRafael Davila ·Marie,
A Contractual Baseline is a reference schedule for comparison purposes, is meant to be frozen in time, not to be updated.
The initial Baseline represents your initial plan prior to any updating. It will not be updated but replaced when it longer does not serve its purpose for comparison, maybe after several periodic schedule updates. You re-baseline when needed using the latest updated schedule, here you show revised scope of work, new activities and recovery plan if needed. Upon approval it becomes the new Baseline; this schedule will show actual dates prior to re-baseline schedule DD. Do no leave out Owner delays as this might waive your right for future claims.
When looking for actual dates you look at the current schedule.
When updating your schedule you leave your Baseline intact, even when you re-baseline you leave it intact and keep it as is for future reference, you re-baseline updating your updated job to an agreed DD update.
You still can do minor adjustments to your old Baselines by detaching them. If you change actual dates then in order to make sense the schedule should be recomputed. Do this with caution and always keep a backup of all Contractual Baseline versions.
http://www.warnercon.com/articles/Article%2012%20-%20Recovery%20Schedules.pdf
Best Regards,
Rafael - 0ZQZq qz ·The problem is this. I have a current schedules with actuals on it. Then I want to use this as a baseline itself. Question is why BL Finish dates are not the same with the start date for activities with actual start dates. ( since this is just the mirror image of the current schedule... I just maintain baseline and assign it).
- 0RDRafael Davila ·I don’t have P6, maybe the following reference can give you some light.
http://ronwinterconsulting.com/Understanding_P6_Dates.pdf
“The P6 Early Start, Early Finish, Late Start, and Late Finish (Early/Late Start/Finish) columns are presented differently from their counterparts in Microsoft Project™ or P3. After the CPM calculations are complete, Microsoft Project blanks out all calculated date entries for completed activities. P3 actually deletes the calculated dates for completed activities and replaces those computed dates with the established actual dates. This substitution has led scheduling experts to conclude that the actual dates were not used in computing the current CPM schedule dates. Beginning with their Version 5.0 software release, P6 took a third tact and dares to show calculated dates, even for completed activities.”
Also check on the setup of your baseline bars, this you can modify to your needs. You can decide if using ES/EF dates or Start/Finish dates. Also to show or not to show float bar. I used to display my float bars from ES to LF instead of from EF to LF, is up to you.
Best regards,
Rafael - 0MMMark M ·Hi Marie
I am guessing that under your admin preferences, Earned Value tab, the Earned Value Calculation drop down box is set to Budgeted Values with Planned Dates. If you have admin rights or can convince admin to change this, I suggest you set it to "Budgeted Values with Current Dates".
P6 uses this to determine which dates to show for the baseline (although they don’t document this anywhere...) Therefore if set to Planned Dates that is what you are seeing for statused activities, & not the Actual.
Hope that helps & solves your issue.
Regards
Mark