Dear Friends
Nw Iam making one base program in the P6.

When Iam giving the start to start relation with one activity .Instead of starting the same predecessor activity .Its is showing starting from the next day...

Whats the problem.Please help me to solve this problem.

With regards
Arun Vasanth

4 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Arun,

    Maybe you need to check the modeling again and try to model your program with FS instead of SS activities.

    The Definition of Start to Start means that the initiation of the work of the successor schedule activitiy depends upon the initiation of the work of the predecessor schedule activity. Is this what you actually want!

    With kind regards,

    Samer
  2. 0
    Rafael Davila ·
    Take a look at the thread title: CALENDAR

    Maybe your activities have different calendars, also make sure there is no relationship lag.
  3. 0
    Cornelis van Klaveren ·
    Pls check your Start and Finish Colum.
    They should show the date and TIME.

    Otherwise P6 is not counting the first day.

    See also the DATES Articel on this site.
    It explains a lot about working whit dates.
  4. 0
    Rafael Davila ·
    http://www.ronwinterconsulting.com/Understanding_P6_Dates.pdf