Skip to content

Import Resources in P6 by importing Excel spreadsheet

Kinnar PatelMember for 20 years 4 months
Created
10
1
0
Hi Everyone,
Does anyone know that how to assign resources to P6 programme by an excel spreadsheet and importing it in P6.
Is there any add-on available for P6 to do this.
I will appreciate your help.
Thanks in advance.
Kinnar

10 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Kinnar

    Why not just copy / paste from excell to P6?

    Best regards

    Mike Testro
  2. 0
    Kinnar Patel ·
    How?
  3. 0
    Mike Testro ·
    Hi Kinnar

    If you have any data in an excell column and the numbers line up with the activities on the chart you should be able to copy the excell data and paste it into the corresponding column in P6.

    I do this all the time with PowerProject.

    Best regards

    Mike Testro.
  4. 0
    Rafael Davila ·
    Mike,

    Some values are related to other values; if you only copy a portion you might damage the database or make it invalid. A resource definition is tied to calendars. What if the calendar does not exists? What if calendar definitions are different but equal names?

    If you change resources using existing resources there would be no issue but I believe here the intention is to bring resources from another job.

    It is not as simple as copy and paste. I would not rely on software that allows you to do that. Remember by merely missing a line in the sequence you would induce great error. In order to do it appropriately a key field must be used.

    Recommend you cross with magic marker this option in your screen.

    You can write my name on an exel spreadsheet paste it and then tell me about my birthday, this day must be defined as a personal holiday. Well Poweproject is a cristal ball.

    Best regards,
    Rafael
  5. 0
    Ferdinand U. ·
    hi kinnar

    you can try using export import to spreadsheet facility of p6 from file menu

    or you can try activity6x.xls
  6. 0
    Kinnar Patel ·
    Hi,
    How to use activity6x.xls?
    Please let me know.
  7. 0
    Ferdinand U. ·
    you need SDK installed

    then just experiment with the excel file
  8. 0
    Mike Testro ·
    Hi Rafael

    I use copy paste all the time between the Powerproject spreadsheet columns and Lotus 123 columns.

    I have to ensure that the the two sets of coulmns line up precisely but after that it is routine.

    If I change a set of data - such as resource hours totals - the underlying calendars allocated to the task remain unchanged.

    Since most of my delay analysis work is done on lotus 123 (80%) then this facility is very useful.

    Best regards

    Mike Testro
  9. 0
    Muhammad Anwar ·
    Kinnar

    You need to install SDK from primavera disk.
    Put the disk 1 in and run the exe file. Then choose to modify and hit next. You will have the option to install sdk there.
    Once you installed SDK with pubuser name and password and it has been configured.
    Then run the activity6 file if are on p6 and enable the macro in the spreadsheet.
    Put in admin as username and password if your username and password are default for P6
    Then hit the update project button. It will connect to PMDSDK and update the list.
    The select the appropriate project and hit the Get... button
    and update informaton in editable field without touching read only fields. Then hit the Set... buttons to update.

    Hope this will help.

    regards
  10. 0
    Johnny Xu ·

    WONDERFUL Post.thanks for

    WONDERFUL Post.thanks for share..extra wait .. … Play blackjack infestation Mobile Porn pollutant Mobile Porn roadbed Free Mobile Porn neurosensory government grants dividendi win palace Catchall

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?