Importing Budgeted Labour Unit

Susan YoungMember for 23 years 7 months
Created
2
3
0
Hello Everybody,

I have an issue with importing Budgeted Labour units.

In my schedule I have Budgeted Labour units currently defiend in a UDF column. I am trying to export it in Excel and then re-import the values as Budgeted Labour Units.. (I have already assigned a resource to the activities).
However it doesnt work.

Any suggestions would be very helpful.

Thanks

Sue

2 replies

Oldest first
  1. 0
    Izam Zakaria ·
    Sue,

    Use resource resourcement option then upload your BQ onto ’Budgeted Units(h)column. Ensure the resource have beed assigned.

    Cheers
  2. 0
    Arnold Puy ·
    Hi Susan,

    You have two option to perform the Resource Loading:

    Export it to Excel with two "Export Type" e.g. Activities & Resource Assignments.

    1. Under Activities include the UDF in the Selected Option.
    2. Under Resource Assignments include the "Budgeted Units" in the Selected Option.

    Or you can perform a Global Change, however your UDF must be under the "Activity Resource Assignments" Fields. and the Parameters should look like this:

    Where UDF Title "is not equal" (Blank)
    Then Budgeted Labor Units " = " UDF Value

    Note: Blank means "No Value" at all.

    Otherwise, if it ok for you to send the .xer file to primavera6@live.com and I will fix it for you.

    Regards,

    Arnold

Log in or join to reply