Importing Budgeted Labour Unit
In the Open Standard
Susan YoungMember for 23 years 7 months
- Created
- 2
- 3
0
Hello Everybody,
I have an issue with importing Budgeted Labour units.
In my schedule I have Budgeted Labour units currently defiend in a UDF column. I am trying to export it in Excel and then re-import the values as Budgeted Labour Units.. (I have already assigned a resource to the activities).
However it doesnt work.
Any suggestions would be very helpful.
Thanks
Sue
I have an issue with importing Budgeted Labour units.
In my schedule I have Budgeted Labour units currently defiend in a UDF column. I am trying to export it in Excel and then re-import the values as Budgeted Labour Units.. (I have already assigned a resource to the activities).
However it doesnt work.
Any suggestions would be very helpful.
Thanks
Sue
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?