P6.1 Logic Report that shows Act. Cal. assignment

Trevor WilliamsMember for 17 years 7 months
Created
1
2
0
Does anyone have a custom Pred. / Succ. report written for P 6.1 (or similar version) that shows the following information for the activity itself, as well as each of it’s Pred.’s & Succ.’s;

- Activity ID
- Activity Name
- OD
- RD
- Start
- Finish
- Relationship Type
- Lag
- Critical
- Total Float
- Driving
- Activity Calendar

I would be very grateful if anyone could share this report if they have it.

1 reply

Oldest first
  1. 0
    Ian Nicholson ·
    You can create this in the report wizard. Choose new report, Activities with sub-elements Predecessors and Successors and then choose your fields for each report element.

    Send me a message if you can’t get it to work and I’ll send a report to you. I’m running 7.0, so the formats may not be compatible but you can still create this in 6.1.

    Ian

    http://www.emerald-associates.com

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?