Importing a project gives different resources??

John GouldenMember for 23 years 10 months
Created
3
2
0
I have a number of projects in P6 with resources. On importing a project file (xmr)I have found that resources previously allocated to other projects are now to be found on activities within the new project.

And when I compare the resource allocation on activities on the source laptop with mine (with the imported file) - they are totally different!!!???

Does anybody have any ideas?

3 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear John,

    These problems occur when you have different units. Please check the format and unit at each source.

    With kind regards,

    Samer
  2. 0
    John Goulden ·
    Samer thanks for that.

    Since posting the original query we’ve set the user and admin preferences to be the same on both the source laptop and the destination laptop.

    Still no further forward.

    In the destination laptop the file is showing a resource from an entirely different project.....?

    And all the imported resource calendars are a complete buggers muddle.

    We are loosing the will to live!
  3. 0
    Ian Nicholson ·
    When you do the import, do you have the import resources options set to "Keep existing" or "Update Existing"? These cause problems when the system finds a resource with the same name already exists within the target machine.

    To check, set the option to "Create New" and see if the problem is resolved.

    Calendars could well be a similar problem.

    Ian

    http://www.emerald-associates.com