Global change (If-Then-Else(If-Then-Else))
In the Open Standard
Alexandre Faulx-BrioleMember for 23 years 8 months
- Created
- 2
- 1
0
Hello Planners,
I would like to automatize some Indicator-UDF: Green when an activity is on track, Yellow when schedule duration is less than Baseline Duration * 150%, Red when schedule duration is more than Baseline Duration * 150%.
I will of course have P6 calculate the indicator with a Global Change
I cannot insert a second If statement if the Else panel; is there a way to do this, or any work-around?
Thanks for your help,
Alexandre
I would like to automatize some Indicator-UDF: Green when an activity is on track, Yellow when schedule duration is less than Baseline Duration * 150%, Red when schedule duration is more than Baseline Duration * 150%.
I will of course have P6 calculate the indicator with a Global Change
I cannot insert a second If statement if the Else panel; is there a way to do this, or any work-around?
Thanks for your help,
Alexandre
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?