Possible Global change
In the Open Standard
Salman AhmedMember for 16 years 7 months
- Created
- 5
- 2
0
Hi all,
Last week updated schedule is attached as baseline to the Current Schedule.
I would like to add a new UDF (Weekly accomplishment).This shall be the difference of the Current schedule activity % - BL activity % complete.
What Global change shall I apply for this.
Thanks in advance
Last week updated schedule is attached as baseline to the Current Schedule.
I would like to add a new UDF (Weekly accomplishment).This shall be the difference of the Current schedule activity % - BL activity % complete.
What Global change shall I apply for this.
Thanks in advance