Skip to content

Possible Global change

Salman AhmedMember for 16 years 7 months
Created
5
2
0
Hi all,

Last week updated schedule is attached as baseline to the Current Schedule.

I would like to add a new UDF (Weekly accomplishment).This shall be the difference of the Current schedule activity % - BL activity % complete.

What Global change shall I apply for this.

Thanks in advance

5 replies

Oldest first
  1. 0
    Ferdinand U. ·
    Try

    UDF EQ Activity % complete - Schedule % COmplete
  2. 0
    Mai Tawfeq ·
    please guys anyone can explain me what does mean global change and what the advantage can be by using it?
  3. 0
    Arnold Puy ·
    Hi Salman,

    In addition to Ferdinand info, try The following:

    1. Create a "Activities" as you User Defined Fields, (Weekly accomplishment) as your Title, and "Number" as your Data Type.
    2. When done, create a new global change with parameters:

    Where:
    Activity Status "is not equal" Not Started

    Then:
    Weekly accomplishment " = " Activity % Complete - Schedule % Complete

    HTH.

    Regards,

    Arnold
  4. 0
    Salman Ahmed ·
    Thanks guys,

    Is this Schedule % complete taken from the baseline’s activity % complete or baselines duration % complete.

  5. 0
    Ferdinand U. ·
    http://www.planningplanet.com/forum/forum_post.asp?fid=&Cat=8&Top=59607

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?