Comparing Work Packages within Multiple P6 Projects
In the Open Standard
Simon DaviesMember for 16 years 10 months
- Created
- 5
- 4
0
I have recently taken over a Programme and I have been asked to illustrate why delays to a specific work package has occurred over the last 13 monthly updates. (This is one work package of 6 in the programme)
Does anyone know a quick report or method of illustrating how the acitivities have moved for the specific work package only? Perhaps coding the acitivities somehow and a group /sort??
P6 only has 3 baselines which it can illustrate graphically so I can’t perform this task visually. Any help would be great.
Does anyone know a quick report or method of illustrating how the acitivities have moved for the specific work package only? Perhaps coding the acitivities somehow and a group /sort??
P6 only has 3 baselines which it can illustrate graphically so I can’t perform this task visually. Any help would be great.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?