Skip to content

Labour units reduces

Salman AhmedMember for 16 years 7 months
Created
3
2
0
When a .xer file is imported the labour units reduces. (are devided by 10). Thanks in advance.

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Salman,
    Check your Time Units setting. It maybe set to day but the xer that you importing is set by hours or vice versa. Check also your calendar if set 10hrs per day.
    Select Edit->User Preferences-> Time Units tab. Check the Unit of time.
  2. 0
    chidhambarathanu Bala ·

    I am working in P5.I work out

    I am working in P5.I work out program in in my system and import XER to another system. The issue is there is some difference in the labour units. The difference 0.8 times than older value. I have checked the calendar assignment and user preference all are same as in my system. Please advice how to rectify the issue. 

  3. 0
    chidhambarathanu Bala ·

    What is effect during

    What is effect during updating, if the duration unit is differ from resource units? i.e. if the duration unit is in “days” and the resource unit is in “Hours”?

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?