FF with lag Relationship Issues
In the Open Standard
Sophia MMember for 16 years 7 months
- Created
- 2
- 1
0
Hi,
I am currently working on a baseline for a design schedule where the design process is broken into three stages: In Progress/100%/and RFC.
I am scheduling the 100% design stage (38day duration) to have a FS relationship with the In-Progress Design process and a FF+15 relationship with the In-progress Review (21 days). The date that is showing is more than 15 days beyond the finish date of the review process. Should the finish date that is shown be driven by the FF+lag relationship or the duration?
I am currently working on a baseline for a design schedule where the design process is broken into three stages: In Progress/100%/and RFC.
I am scheduling the 100% design stage (38day duration) to have a FS relationship with the In-Progress Design process and a FF+15 relationship with the In-progress Review (21 days). The date that is showing is more than 15 days beyond the finish date of the review process. Should the finish date that is shown be driven by the FF+lag relationship or the duration?
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?