Multiple Calendar Scheduling
In the Open Standard
Sophia MMember for 16 years 7 months
- Created
- 5
- 1
0
Hi Everyone,
I am working on a baseline construction schedule which has multiple calendars:
1. 1 shift 8 hour 5 day schedule
2. 2 shift 16 hour 5 day schedule
3. 3 shift 24 hour schedule
4. 24 hour 7 day schedule
5. 1 shift 8 hour 6 day schedule
6. 2 shift 16 hour 6 day schedule
The durations that I am inputting are from the bid ie 5 days on a 1 shift 8 hour calendar or 15 days based on a 3 shift 24 hour calendar. The default calendar is 8 hours.
When I run the schedule, the dates are dramatically shortened despite maintaining the durations. Is this a function of P6?
Is their a solution to this?
I am working on a baseline construction schedule which has multiple calendars:
1. 1 shift 8 hour 5 day schedule
2. 2 shift 16 hour 5 day schedule
3. 3 shift 24 hour schedule
4. 24 hour 7 day schedule
5. 1 shift 8 hour 6 day schedule
6. 2 shift 16 hour 6 day schedule
The durations that I am inputting are from the bid ie 5 days on a 1 shift 8 hour calendar or 15 days based on a 3 shift 24 hour calendar. The default calendar is 8 hours.
When I run the schedule, the dates are dramatically shortened despite maintaining the durations. Is this a function of P6?
Is their a solution to this?
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?