To re-upload BQ onto updated schedule

Izam ZakariaMember for 20 years 4 months
Created
3
1
0
Gents

I’ve an updated schedule with some of them have a progress and some of them are none. The original BQ have been removed and now I want to upload back onto my updated schedule. My question is, what happen to my schedule if I want to upload 500 mhrs onto activity that have 50% physical progress? Is it it will be divided 50-50? Is it any impact onto scheduling analysis? Could you tell me anything bad will happen If I do this.

Guys your future explanation is highly appreciated.

3 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Izam,

    You can either read the manual and figure out the options and how to use them, or your can copy the schedule into a test file and experiment and learn from experimenting. Trying to figure out what will happen in each software is mostly trial and error, unless you read the theory behind it.

    With kind regards,

    Samer
  2. 0
    Rodel Marasigan ·
    Izam,
    If you used Physical on % complete type that will not affect your budget, actual and remaining units. It will not automatically touch those fields but to make sure, check the setting in your resources and have Auto compute actual is not tick.

    You can practice some activities before applying to whole project if you are in doubt.
  3. 0
    Izam Zakaria ·
    good advise, really appreciate it