print out calendar

Izam ZakariaMember for 20 years 4 months
Created
3
1
0
Guys,

Sorry for asking this, how to print out the calendar in P6?

3 replies

Oldest first
  1. 0
    Muhammad Anwar ·
    Izam,

    P6 does not provide the facility to print calendar but workaround to show by putting a long bar at the top of your plan and using necking to show non work periods.

    regards


    Muhammad
  2. 0
    Tim Readman ·

    Izam,better than a work

    Izam,

    better than a work around use comviz which looks into the database and get the out put from there. I have wanted P6 to do this like we used to do in P3 but in the end had to get one produce.

     

    http://comviz.com.au/products/comvizcalendar 

     

    "Comviz Calendar automatically calculates working days depending on the start day. These days do not include non-working days from Oracle Primavera P6 and the days marked as non-working. You can assign different colors and labels for the calendar days in order to create sofisticated calendars." 

     

    Tim

  3. 0
    Anbin Ponnith ·

    TimThanksRegardsAnbin

    Tim

    Thanks

    Regards

    Anbin