Schedule % Complete vs Activity % Complete
In the Open Standard
Irfan KhanMember for 17 years 3 months
- Created
- 5
- 2
0
hi to all,
Can anybody make me understand that what is the difference between Schedule % Complete & Activity % Complete.
Bcz an activity’s activity complete have 6.82% and when i m inserting a column of of Schedule % Complete the same activity showing 9.09%.
so pls tell me logic behind these factors......
thanks in advance......
Can anybody make me understand that what is the difference between Schedule % Complete & Activity % Complete.
Bcz an activity’s activity complete have 6.82% and when i m inserting a column of of Schedule % Complete the same activity showing 9.09%.
so pls tell me logic behind these factors......
thanks in advance......
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?