Schedule % Complete vs Activity % Complete

Irfan KhanMember for 17 years 3 months
Created
5
2
0
hi to all,

Can anybody make me understand that what is the difference between Schedule % Complete & Activity % Complete.

Bcz an activity’s activity complete have 6.82% and when i m inserting a column of of Schedule % Complete the same activity showing 9.09%.

so pls tell me logic behind these factors......


thanks in advance......

5 replies

Oldest first
  1. 0
    Alaa Al haj ·

    Hi
    i am not sure but i think activity percent completion is actual progress
    while schedule percent completion is the scheduled ( planned progress)


    Alaa
  2. 0
    Irfan Khan ·
    thanks All

    i agree but y it is not showing in total bar...?
  3. 0
    Rashid Iqbal ·
    It is the Planned Progress of the Baseline...if as per baseline the activity should have been completed...the ’Schedule Perent’ will show 100%. Thanks.

    r
  4. 0
    Rodel Marasigan ·
    Irfan,
    Their answers are all correct. Schedule % Complete is Baseline Planned % (if have baseline) or current Project Planned % Complete (if no baseline assigned) and Activity % Complete is Actual % complete.

    The reason why it has 0% on summary bands is because you haven’t cost loaded your schedule. P6 calculation of Progress is based on cost.
  5. 0
    Irfan Khan ·
    thanks to all.....

Log in or join to reply