Using Global Change

Carson CrosbyMember for 16 years 5 months
Created
2
2
0
Well my issue is this, I need to Compress my entire schedule into a shorter time frame. We need to keep the Same finish date but push my start date back nearly 6 months. is there any quick way i can accomplish this.

2 replies

Oldest first
  1. 0
    Rashid Iqbal ·
    Yeah I can tell you that run a global change and reduce the durations of all the activties by 30% or whatever....but you know this is not the correct way of doing the things...

    It looks like a case of major replanning...so start all over again. Thanks.

    R


  2. 0
    David Andreotti ·
    You can do a global change but as Rashid said, this is NOT the right way to do this. Yo uneed to keep stepping back through the critical path (which may change frequently during this exercise) to see if there’s some bad logic, etc. Make sure there are no resources driving the scheudle out, etc.

    Without looking at the schedule, it’s difficult to tell you how to handle it. good Luck!