scheduled % complete vs actual % complete

Kumar SMember for 16 years 8 months
Created
4
2
0
Dear All,

please guide me


In the activity report layout i am comparing the schedule % complete with the actual % complete.

for the schedule % complete in the summary bar it is showing as 0 % complete even if the activites are 100% complete.
why is this happening ...

here is the link to the snap shot of my layout ...
http://img687.imageshack.us/img687/5333/newbitmapimage3g.png


please help me guys...

4 replies

Oldest first
  1. 0
    Ali Farhat ·
    I dont have a good explanation, but you’ld better check the technique for computing performance % complete @ WBS window for your baseline schedule. I think the problem is there..if there is a problem
  2. 0
    Rodel Marasigan ·
    satishan,
    The reason is because you program is not cost loaded. P6 calculates % Complete using budget cost.
  3. 0
    Kumar S ·
    Dear Rodel,

    you are correct that the project is not cost loaded.
    but how can we get the schedule % complete without the cost load.for the previous project the % is showing correctly in the summary bar.
    for this project only there is a problem.
    is there any ting to do for the resource allocation or some settings has changed...


    Satishan....
  4. 0
    Rodel Marasigan ·
    Satishan,
    If you looked at the previous project, you find it is cost loaded. It may using only dummy cost to weight the activities. Below is link for some example on how to cost load you activities.

    Weight Post#2

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?