Calculation of % Complete at Summary Level

Ijaz AhmadMember for 20 years 3 months
Created
1
1
0
Hello guys,
Can anybody tell me how P6 calculates the performance % complete at summary Level when we are using it for our Earned Value report.
Thanks
Ijaz

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Ijaz,
    Performance % complete = Activity % complete * BAC. Meaning weighting of each activity base on cost * % complete.