Role Price/Unit not able to get in Resources
In the Open Standard
Haresh JayanthMember for 20 years 1 month
- Created
- 1
- 3
0
Hi,
I have created a role namely "Site Engineer" and then i have created a resource Mr. "X".
I have given price/Unit for the roles for example $200/h to the role. But , when i assign this resource i.e. Mr. X to the role, the price / unit assigned to the roles is not shown in price/unit of the resources?
I want to know the reasons,why does price / unit which was assigned to the role,is not taken by the resource , if the said resources is assigned to the role??
Can anybody have better explanation?
Moreover , My understanding of roles and OBS , are that roles can be assigned to an activity but OBS can be assigned only to WBS, that is the only difference between roles and OBS, is my thinking correct, if not kindly explain.......
I have created a role namely "Site Engineer" and then i have created a resource Mr. "X".
I have given price/Unit for the roles for example $200/h to the role. But , when i assign this resource i.e. Mr. X to the role, the price / unit assigned to the roles is not shown in price/unit of the resources?
I want to know the reasons,why does price / unit which was assigned to the role,is not taken by the resource , if the said resources is assigned to the role??
Can anybody have better explanation?
Moreover , My understanding of roles and OBS , are that roles can be assigned to an activity but OBS can be assigned only to WBS, that is the only difference between roles and OBS, is my thinking correct, if not kindly explain.......
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?