S-Curve

Ruel CamaquinMember for 17 years 11 months
Created
6
2
0
Guys,

Just like to know if, Is it possible to generate a S-Curve in a schedule that do have any resources?

Thanks in advance to those that will be responding to this query..

Cheers!

6 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Click the link below to download the steps which is published on the other thread with same topic.
    Step On How to Produce S-Curve & Histogram
  2. 0
    Irfan Khan ·
    Ruel,

    U can generate S-Curve in P6. Just follow these steps:-

    >>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
    > Go to View > Show on Bottom > Resource Usage Profile

    > Select any one resource what u defined & u wanted to show in as a S-Curve

    > Right Click on the open Space Area of Histogram.

    >mark the Cumulative Box for Budgeted & Actual depending on your requirments.
    >>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

    regards,,,,,





  3. 0
    Ruel Camaquin ·
    Guys,

    Thanks for your quick response, but how about if you schedule if is just activity driven and do not have any resources?

    Again thanks a lot guys!

    Cheers!

    Ruel
  4. 0
    Joseph Ador ·
    Ruel,

    you can’t produce the S-curve or histogram without any resources assigned to the project activities. As you can see by following the steps given below, you are ask to check either you will show the s-curve/histogram based on units/cost of nonlabor. materials and labor assignments. Therefore it must be primarily comes from your resources assigned.

    Regards,
    Josh
  5. 0
    Ruel Camaquin ·
    Guys,

    Thank you for the enlightment on the matter, now all i need is to convince my boss that it is not possible!

    Cheers!

    Ruel
  6. 0
    Rodel Marasigan ·
    Ruel,

    Below link is a good approach if Project is Activity Driven. I explain 3 options that you can use.
    Duration % Complete Post #3

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?